Late-autumn trees and landscaped condominium frontage beside a quiet street in Mississauga, with warm light on pale stone and amber leaves.

Hazel McCallion Line Construction in Mississauga: Plan Your Drive

This fall, LRT construction on Hurontario Street has followed a clear pattern. Metrolinx posts a notice for a cross street, closes that intersection for a night, a weekend or a few days, and then opens it again. Two jobs break the pattern during the week this post goes up. Harborn Road and North Service Road have been closed to cross traffic since mid-October, and the Eaglewood Boulevard work near Mineola Road runs through the weekend. Once you know the pattern, it's much easier to plan your errands and commute around the work.

How far along the line is

The Hazel McCallion Line will run 18 km with 19 stops, from Port Credit GO in Mississauga to the Brampton Gateway Terminal at Steeles Avenue. On August 11, 2026, Metrolinx president and CEO Michael Lindsay gave CityNews a progress report. About 75 percent of the track work was done, 8 of the line's 14 traction power substations were energized, and so was the maintenance and storage facility.

He also gave a timeline. "We hope to have all civil infrastructure on this project complete by roughly this time next year," Lindsay said, adding that the line would then move into the kind of testing phase seen on the Eglinton and Finch lines. That puts the end of major construction around August 2027. Passenger service comes after testing. INsauga reported that earlier estimates for the opening pointed to 2028.

The first trains have already moved on the tracks. From August 11 to 18, 2026, Metrolinx ran light rail vehicles at low speed from the operations facility along Edwards Boulevard and Topflight Drive to Hurontario Street. INsauga put the testing speed at 10 km/h. Lindsay told CityNews that these early trial runs draw on lessons from the Eglinton Crosstown and Finch West projects and are meant to speed up system integration testing.

What's left is mostly finishing work, and that changes how closures look on the street.

The fall pattern: short closures, posted ahead

Here are the cross-street closures Metrolinx posted between September and mid-November:

Cross street at Hurontario Closure window Shape
Bristol Road Fri. Sept. 11, 7 p.m. to Mon. Sept. 14, 7 a.m. Weekend, full closure both sides
Barondale Drive Mon. Sept. 14, 7 p.m. to Wed. Sept. 16, 5 a.m. Two overnights
Burnhamthorpe Road Fri. Sept. 25, 9 p.m. to Mon. Sept. 28, 6 a.m. Weekend, full closure both sides
Eglinton Avenue Until Mon. Oct. 26, 6 a.m. Weekend, partial closure
Harborn Road / North Service Road Tues. Oct. 13, 10 p.m. to Tues. Nov. 17, 10 p.m. Five weeks, no cross traffic
Agnes Street Full closure Mon. Nov. 9 Single day
Eaglewood Boulevard Wed. Nov. 11 to Mon. Nov. 16 Turn limits, lane shifts, overnight closures

The two full closures, at Bristol and Burnhamthorpe, ran from Friday night to early Monday. Most of the others lasted a night or a few days. Harborn is the exception. The notices usually go up about a week ahead. The Bristol and Barondale notices were dated September 4 for closures that began September 11 and 14. The Agnes notice was dated October 28 for work starting November 2, and the Eaglewood notice was dated November 5 for work starting November 11. If you check the Metrolinx Hazel McCallion Line page every few days, you'll usually see upcoming closures before they start.

The notices also come with ready-made detours. For the Bristol closure, drivers were sent along Matheson, Kennedy, McLaughlin and Eglinton, and MiWay Route 10 was detoured. For Burnhamthorpe, traffic went around on Confederation Parkway and Central Parkway West. When Eglinton closed in October, MiWay routes 17, 35, 103 and 135 ran detours. Every notice says work may be rescheduled because of weather, so treat the posted dates as plans.

The two exceptions this week

Harborn Road and North Service Road, through November 17

Crews have been welding track and pouring concrete for the guideway right in the middle of this intersection. Until 10 p.m. on Tuesday, November 17, east-west traffic can't cross Hurontario at Harborn Road and North Service Road in either direction. Left turns aren't allowed, but right-in and right-out access stays open. Metrolinx says detours are posted on site and that emergency access isn't available through this intersection while it's closed.

If you live east or west of Hurontario near the QEW, the main thing to remember is that you can reach Hurontario but you can't cross it here. Plan any crossing at the next signal for a few more days.

Eaglewood Boulevard, November 11 to 16

At the south end of the corridor, crews are putting in new sanitary infrastructure at Eaglewood Boulevard and then milling and repaving the road. The work runs around the clock from Wednesday, November 11 to Monday, November 16. Here's how it plays out day by day:

  1. November 11 to 16: left-turn restrictions, lane shifts and overnight closures at Eaglewood Boulevard.
  2. November 13 to 15: Hurontario Street drops to a single lane, with a flagger alternating northbound and southbound traffic.
  3. November 14 to 16: more restrictions, with detours on Mineola Road, Eaglewood Boulevard and Inglewood Drive.
  4. Throughout: the Hurontario driveway into the plazas north of Eaglewood Boulevard is closed.

Unlike at Harborn, emergency access is maintained here. Metrolinx also says it will aim equipment lights away from homes and take steps to keep dust down. If you shop at the plazas just north of Eaglewood, plan for that driveway to stay closed until the work wraps up on Monday.

Through December 31: the central stretch gets busier

Metrolinx's October 6 notices for Cooksville, Mississauga Centre and Mississauga North all cover October 1 through December 31. Between Burnhamthorpe and Eglinton, the list includes track, electrical and telecommunications work, landscaping, roadwork and stop shelters. Light rail vehicle testing and energizing the stops are listed as work still to come. The Cooksville notice covers Harborn Road to Burnhamthorpe, with track finishing, restoration, a signal switchover, stop installation and substation energizing.

According to INsauga's October 23 report, work between Burnhamthorpe and Eglinton will pick up through year-end. Crews will be working on track, the guideway over Highway 403, utility cutovers, stops, the overhead wires the trains run on, and bus stop upgrades at the terminal. Metrolinx says some temporary road closures and driveway impacts may happen during this period. If they follow the fall pattern, they'll be posted about a week ahead.

Shelters, wires and energized stops are a sign of progress. When stops start going live, the corridor is getting close to the testing phase Lindsay described.

What riding will look like once it opens

Metrolinx's June 26, 2026 town hall Q&A projects a train every 7.5 minutes at peak times and every 10 to 12 minutes off-peak. The same document says a first-rider promotion will be decided closer to opening.

The fare depends on provincial fare-alignment work involving Mississauga and Brampton, which Global News covered this spring. In the meantime, MiWay buses charge the 2026 MiWay fares. Under the City's 2026 fare schedule, effective January 1, 2026, that's $3.50 for adults paying with PRESTO and $4.50 cash. Paying with PRESTO saves you a dollar a trip over cash right now. MiWay's fare page also lists free connections to GO on PRESTO.

For the next few weeks, if you're driving: you can't cross Hurontario at Harborn until the evening of November 17, Hurontario at Eaglewood is down to one lane from Friday to Sunday, and the posted notices usually show the next closure about a week ahead.

If you live near Hurontario and want to talk through how the line could affect a future sale, purchase or rental, we know this corridor well and we're glad to help. Get in touch with The Camara Team by clicking Contact Us.

A Legacy You Can Rely On

The Camara Team’s approach is rooted in experience, personal service, and relationships that continue long after a transaction. With generations of family involvement and a business built largely through referrals, clients receive dedicated guidance from people who genuinely care about their next move.

Follow Me on Instagram